<?xml version="1.0" encoding="UTF-8"?><rss version="2.0"
	xmlns:content="http://purl.org/rss/1.0/modules/content/"
	xmlns:wfw="http://wellformedweb.org/CommentAPI/"
	xmlns:dc="http://purl.org/dc/elements/1.1/"
	xmlns:atom="http://www.w3.org/2005/Atom"
	xmlns:sy="http://purl.org/rss/1.0/modules/syndication/"
	xmlns:slash="http://purl.org/rss/1.0/modules/slash/"
	>

<channel>
	<title>Reper24 &#187; management al deșeurilor</title>
	<atom:link href="https://arhiva.reper24.ro/etichete/management-al-deseurilor/feed/" rel="self" type="application/rss+xml" />
	<link>https://arhiva.reper24.ro</link>
	<description>ultimele stiri din resita si caras severin</description>
	<lastBuildDate>Tue, 29 Sep 2026 07:23:10 +0000</lastBuildDate>
	<language>ro-RO</language>
		<sy:updatePeriod>hourly</sy:updatePeriod>
		<sy:updateFrequency>1</sy:updateFrequency>
	<generator>https://wordpress.org/?v=4.0.33</generator>
	<item>
		<title>Ce se întâmplă cu proiectul de zeci de milioane de euro, demarat pe vremea lui Sorin Frunzăverde?</title>
		<link>https://arhiva.reper24.ro/ce-se-intampla-cu-proiectul-de-zeci-de-milioane-de-euro-demarat-pe-vremea-lui-sorin-frunzaverde/</link>
		<comments>https://arhiva.reper24.ro/ce-se-intampla-cu-proiectul-de-zeci-de-milioane-de-euro-demarat-pe-vremea-lui-sorin-frunzaverde/#comments</comments>
		<pubDate>Tue, 07 Jan 2020 12:20:46 +0000</pubDate>
		<dc:creator><![CDATA[Karina Tincul]]></dc:creator>
				<category><![CDATA[ADMINISTRAŢIE LOCALĂ]]></category>
		<category><![CDATA[ŞTIRILE ZILEI]]></category>
		<category><![CDATA[Caraş-Severin]]></category>
		<category><![CDATA[deponeu]]></category>
		<category><![CDATA[deseuri]]></category>
		<category><![CDATA[frunzaverde]]></category>
		<category><![CDATA[google]]></category>
		<category><![CDATA[hala sortare]]></category>
		<category><![CDATA[levigat]]></category>
		<category><![CDATA[lupac]]></category>
		<category><![CDATA[management al deșeurilor]]></category>
		<category><![CDATA[Reper 24]]></category>
		<category><![CDATA[reper24.ro]]></category>
		<category><![CDATA[Silviu Hurduzeu]]></category>
		<category><![CDATA[stiri caraș-severin]]></category>

		<guid isPermaLink="false">http://reper24.ro/?p=85807</guid>
		<description><![CDATA[Centrul integrat de management al deșeurilor de la Lupac este încă departe de momentul în care va deveni operațional, cu toate că acesta ar fi trebuie să funcționeze deja de câțiva ani de zile. Proiectul de implementare a unui sistem integrat de management al deșeurilor în județul Caraș-Severin, în valoare de zeci de milioane de [&#8230;]]]></description>
				<content:encoded><![CDATA[<p><a href="https://arhiva.reper24.ro/wp-content/uploads/2020/01/lupac.jpg" rel="lightbox[85807]"><img class="aligncenter size-full wp-image-85809" src="https://arhiva.reper24.ro/wp-content/uploads/2020/01/lupac.jpg" alt="lupac" width="1024" height="576" /></a></p>
<p>Centrul integrat de management al deșeurilor de la Lupac este încă departe de momentul în care va deveni operațional, cu toate că acesta ar fi trebuie să funcționeze deja de câțiva ani de zile. Proiectul de implementare a unui sistem integrat de management al deșeurilor în județul Caraș-Severin, în valoare de zeci de milioane de euro, a fost „moștenit” de actuala conducere a forului județean, fiind demarat pe vremea în care la frâiele județului se afla Sorin Frunzăverde. De atunci au trecut ani de zile în care deschiderea centrului era anunțată de la o lună la altă. Inclusiv ministrul Mediului a trecut pe la un moment dat (în 2018) prin județ și a dat un termen limită pentru ca deponeul de la Lupac să devină operațional. Degeaba însă, lucrurile par să treneze la nesfârșit atunci când vine vorba de acest proiect. Să fie vorba de ghinion, lipsă de interes și voință sau pur și simplu incompetență?</p>
<p><span id="more-85807"></span></p>
<p>În ședința din luna decembrie a Consiliului Județean Caraș-Severin a fost prezentată o informare privind situația centrului de management integrat al deșeurilor de la Lupac. „<em>Investițiile din cadrul proiectului au fost finalizate și recepționate, operarea sistemului nu a fost demarată ca urmare a unor neconformități apărute în perioada de notificare a defectelor</em>”, se arată în raportul în care sunt prezentate în detaliu și defecțiunile majore apărute pe amplasamentul centrului.</p>
<p>Prima problemă s-a ivit încă din mai 2018, atunci când s-a constatat dislocarea bazinului de egalizare levigat. Executantul a încercat remedierea problemei, dar situația s-a degradat, iar bazinul s-a ridicat deasupra terenului cu aproximativ 1,79 m. Problema nu a fost rezolvată nici până acum, deși într-un final, după realizarea unei expertize tehnice (conform căreia problema a fost cauzată de o greșeală de proiectare), realizarea unui nou proiect tehnic care să prevadă refacerea în totalitate a bazinului și scoaterea la licitație atât a lucrărilor, cât și a serviciilor de dirigenție de șantier pentru supervizarea acestora, a fost găsit un nou constructor. Durata de execuție a lucrările este de cinci luni de zile.</p>
<p>O altă defecțiune majoră apărută la centrul de la Lupac este avaria produsă la hala de sortare, mai exact dislocarea acoperișului. În raportul semnat de arhitectul șef Victor Naidan și directorul executiv Cristian Bîtea, se arată exact ce s-a întâmplat la respectiva hală: șarpanta s-a dislocat și se sprijină pe cabinele de sortare, stâlpii de beton perimetrali au fost deplasați spre exterior, a fost afectată închiderea perimetrală a halei și luminatoarele laterale prin deplasarea spre exterior, tubulatura instalațiilor de ventilație ale cabinelor de sortare a fost dezmembrată și deteriorată, instalația electrică fixată de șarpantă a fost angrenată de dislocarea acesteia, instalația de stingere a incendiului, rețeaua de conducte și sprinclere a fost de asemenea dislocată de avarierea șarpantei. Și în acest caz a trecut deja un an de zile de la apariția problemei, fără ca aceasta să fie soluționată.</p>
<p><em>„Așteptăm proiectul pentru reparația halei, care găzduiește stația de sortare. Am avut un diferend cu firma, cu constructorul, legat de soluția propusă și de soluțiile pe care domniile lor le solicitau și le-am explicat faptul că nu pot pune ei condiții, ci ei vor trebui să predea hala la parametri pe care îi avea în momentul în care contractul a fost atribuit acestei firme de construcții. Firma va trebui să depună proiectul tehnic ce urmează a fi analizat la nivelul Consiliului Județean, după care să treacă la execuție. În acest moment, sunt depășite toate termenele pe care și le-au asuma în relația cu Consiliul Județean”,</em> preciza la finalul ședinței președintele forului județean, Silviu Hurduzeu.</p>
<p>Deci când va deveni operațional deponeul de la Lupac? Greu de spus în aceste condiții, dar cel mai probabil acest lucru nu se va întâmpla în următoarele luni, mai ales având în vedere că după finalizarea lucrărilor, va fi necesară și o perioadă pentru verificarea funcționalității sistemului integrat.</p>
<p>&nbsp;</p>
<p><strong>Karina TINCUL</strong></p>
<p><a class="a2a_button_facebook" href="https://www.addtoany.com/add_to/facebook?linkurl=https%3A%2F%2Farhiva.reper24.ro%2Fce-se-intampla-cu-proiectul-de-zeci-de-milioane-de-euro-demarat-pe-vremea-lui-sorin-frunzaverde%2F&amp;linkname=Ce%20se%20%C3%AEnt%C3%A2mpl%C4%83%20cu%20proiectul%20de%20zeci%20de%20milioane%20de%20euro%2C%20demarat%20pe%20vremea%20lui%20Sorin%20Frunz%C4%83verde%3F" title="Facebook" rel="nofollow noopener" target="_blank"></a><a class="a2a_button_facebook_messenger" href="https://www.addtoany.com/add_to/facebook_messenger?linkurl=https%3A%2F%2Farhiva.reper24.ro%2Fce-se-intampla-cu-proiectul-de-zeci-de-milioane-de-euro-demarat-pe-vremea-lui-sorin-frunzaverde%2F&amp;linkname=Ce%20se%20%C3%AEnt%C3%A2mpl%C4%83%20cu%20proiectul%20de%20zeci%20de%20milioane%20de%20euro%2C%20demarat%20pe%20vremea%20lui%20Sorin%20Frunz%C4%83verde%3F" title="Facebook Messenger" rel="nofollow noopener" target="_blank"></a><a class="a2a_button_whatsapp" href="https://www.addtoany.com/add_to/whatsapp?linkurl=https%3A%2F%2Farhiva.reper24.ro%2Fce-se-intampla-cu-proiectul-de-zeci-de-milioane-de-euro-demarat-pe-vremea-lui-sorin-frunzaverde%2F&amp;linkname=Ce%20se%20%C3%AEnt%C3%A2mpl%C4%83%20cu%20proiectul%20de%20zeci%20de%20milioane%20de%20euro%2C%20demarat%20pe%20vremea%20lui%20Sorin%20Frunz%C4%83verde%3F" title="WhatsApp" rel="nofollow noopener" target="_blank"></a></p>]]></content:encoded>
			<wfw:commentRss>https://arhiva.reper24.ro/ce-se-intampla-cu-proiectul-de-zeci-de-milioane-de-euro-demarat-pe-vremea-lui-sorin-frunzaverde/feed/</wfw:commentRss>
		<slash:comments>8</slash:comments>
		</item>
		<item>
		<title>Proiectul de deșeuri, în valoare de peste 40 de milioane de euro, în parametri de siguranță!</title>
		<link>https://arhiva.reper24.ro/proiectul-de-deseuri-valoare-de-peste-40-de-milioane-de-euro-parametri-de-siguranta/</link>
		<comments>https://arhiva.reper24.ro/proiectul-de-deseuri-valoare-de-peste-40-de-milioane-de-euro-parametri-de-siguranta/#comments</comments>
		<pubDate>Wed, 03 Jun 2015 12:56:48 +0000</pubDate>
		<dc:creator><![CDATA[Karina Tincul]]></dc:creator>
				<category><![CDATA[ADMINISTRAŢIE LOCALĂ]]></category>
		<category><![CDATA[ŞTIRILE ZILEI]]></category>
		<category><![CDATA[Bozovici]]></category>
		<category><![CDATA[lupac]]></category>
		<category><![CDATA[management al deșeurilor]]></category>
		<category><![CDATA[Pojejena]]></category>
		<category><![CDATA[reper24.ro]]></category>
		<category><![CDATA[stație transfer deșeuri]]></category>
		<category><![CDATA[victor naidan]]></category>

		<guid isPermaLink="false">http://reper24.ro/?p=27498</guid>
		<description><![CDATA[Lucrările la proiectul privind realizarea sistemului integrat de management al deșeurilor în județul Caraș-Severin sunt în grafic, dau asigurări reprezentanții Consiliului Județean Caraș-Severin. Stadiul proiectului a fost prezentat astăzi, în cadrul unei conferințe de presă, susținute la sediul forului județean de arhitectul șef al județului, Victor Naidan.  „Situația contractului de finanțare, în general, dacă ar [&#8230;]]]></description>
				<content:encoded><![CDATA[<p style="text-align: justify;"><a href="https://arhiva.reper24.ro/wp-content/uploads/2015/06/modelmic20.jpg" rel="lightbox[27498]"><img class="aligncenter size-full wp-image-27503" src="https://arhiva.reper24.ro/wp-content/uploads/2015/06/modelmic20.jpg" alt="modelmic" width="1024" height="576" /></a></p>
<p style="text-align: justify;">Lucrările la proiectul privind realizarea sistemului integrat de management al deșeurilor în județul Caraș-Severin sunt în grafic, dau asigurări reprezentanții Consiliului Județean Caraș-Severin. Stadiul proiectului a fost prezentat astăzi, în cadrul unei conferințe de presă, susținute la sediul forului județean de arhitectul șef al județului, Victor Naidan. <span id="more-27498"></span></p>
<p style="text-align: justify;">„<em>Situația contractului de finanțare, în general, dacă ar trebuie să îi fac o caracterizare aș putea spune că este în parametrii de siguranță. Există anumite întârzieri, există probleme ca în orice contract de finanțare, există probleme ale contractelor care sunt rezultate din mersul economiei sau din diverse cauze obiective, există cauze subiective, dar în continuare spun că suntem în zona parametrilor de siguranță</em>”, a afirmat Victor Naidan.</p>
<p style="text-align: justify;">Conform lui Naidan, lucrările prevăzute în contractul de finanțare se vor încheia până cel târziu în decembrie 2015: „<em>Stadiile de realizare ale contractelor sunt cele preconizate pentru momentul actual, au început să se facă într-un ritm susținut și decontările financiare. Lucrările sunt avansate în centrul de la Lupac, unde lucrările de mișcări de teren au fost finalizate, se lucrează deja la halele stațiilor de sortare și stațiilor de transfer, se lucrează la finisajele depozitului pentru a pregăti soluțiile de impermiabilizare</em>”. În ceea ce privește stațiile de sortare, cea de la Oțelu Roșu este în momentul de finalizare, iar la cele de la Bozovici și Pojejena s-au intensificat lucrările.</p>
<p style="text-align: justify;">Proiectul „Sistem integrat de management al deșeurilor în județul Caraș-Severin” are o valoare de peste 40 de milioane de euro și a fost finanțat prin Programul Operațional Sectorial de Mediu. Proiectul prevede construirea unui centru de management integrat al deșeurilor la Lupac și a trei stații de transfer la Pojejena, Bozovici și Oțelu Roșu, precum și închiderea depozitelor neconforme din Caraș-Severin.</p>
<p style="text-align: justify;">Karina TINCUL</p>
<p><a class="a2a_button_facebook" href="https://www.addtoany.com/add_to/facebook?linkurl=https%3A%2F%2Farhiva.reper24.ro%2Fproiectul-de-deseuri-valoare-de-peste-40-de-milioane-de-euro-parametri-de-siguranta%2F&amp;linkname=Proiectul%20de%20de%C8%99euri%2C%20%C3%AEn%20valoare%20de%20peste%2040%20de%20milioane%20de%20euro%2C%20%C3%AEn%20parametri%20de%20siguran%C8%9B%C4%83%21" title="Facebook" rel="nofollow noopener" target="_blank"></a><a class="a2a_button_facebook_messenger" href="https://www.addtoany.com/add_to/facebook_messenger?linkurl=https%3A%2F%2Farhiva.reper24.ro%2Fproiectul-de-deseuri-valoare-de-peste-40-de-milioane-de-euro-parametri-de-siguranta%2F&amp;linkname=Proiectul%20de%20de%C8%99euri%2C%20%C3%AEn%20valoare%20de%20peste%2040%20de%20milioane%20de%20euro%2C%20%C3%AEn%20parametri%20de%20siguran%C8%9B%C4%83%21" title="Facebook Messenger" rel="nofollow noopener" target="_blank"></a><a class="a2a_button_whatsapp" href="https://www.addtoany.com/add_to/whatsapp?linkurl=https%3A%2F%2Farhiva.reper24.ro%2Fproiectul-de-deseuri-valoare-de-peste-40-de-milioane-de-euro-parametri-de-siguranta%2F&amp;linkname=Proiectul%20de%20de%C8%99euri%2C%20%C3%AEn%20valoare%20de%20peste%2040%20de%20milioane%20de%20euro%2C%20%C3%AEn%20parametri%20de%20siguran%C8%9B%C4%83%21" title="WhatsApp" rel="nofollow noopener" target="_blank"></a></p>]]></content:encoded>
			<wfw:commentRss>https://arhiva.reper24.ro/proiectul-de-deseuri-valoare-de-peste-40-de-milioane-de-euro-parametri-de-siguranta/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		</item>
	</channel>
</rss>